Project Details
The Ichthys Field measures approximately 40 kilometres by 20 kilometres and is one of Australia's largest undeveloped gas fields, with reserve estimates of 12.8 trillion cubic feet of gas and 527 million barrels of condensate and an expected operational life of over 40 years.
The Northern Territory Industry Capability Network (NTICN) has signed an agreement with INPEX Browse, Ltd. to undertake the identification of local, Australian and NZ supply and service industries for all procurement and contracting opportunities through FEED - Front End Engineering and Design. The NT office will consequently act as the lead ICN in the organization’s Australian and New Zealand network.
The Ichthys LNG project personnel will carry out FEED as the joint venture works towards making a final investment decision in 2009 and delivering its first LNG shipment in 2014 or 2015.
Offshore
- Offshore production facility and condensate storage facility
- 850 kilometre subsea pipeline to Blaydin Point, Darwin

Coastal facilities
- Harbour and offloading facilities in Darwin Harbour
- Product offloading jetty
Onshore
- Gas receival
- Two LNG trains producing a total of more than 8 million tonnes per annum
- Storage for condensate, LPG and LNG
- Accommodation and administration facilities